
Power & Energy
Summit Power — 335 MW Combined-Cycle Plant Instrumentation Retrofit
Project Completion
August 2026
01
The Challenge
The plant had ageing pneumatic controls and unreliable emissions monitoring, leading to derating and compliance risk.
02
The Approach
Engineered phased migration to a Siemens PCS 7 platform with new CEMS and APC layer.
03
The Solution
Installed in two outages without impacting baseload. Delivered FAT/SAT and full operator training.
04
The Results
Heat rate improved 4.2%, emissions compliance restored, 0 unplanned trips post commissioning.
“PIC executed flawlessly during a critical outage. — Plant Manager”
Executive Validation
Project Impact Report